Fri Mar 3 03:19:34 2023 |
mgb | Runs | | General | |
plunger run # 147
Beam dump 2.5 enA
Collimator 0.9 enA
Run Data = /onlineNEDA_00/xData/hil099/run_0035_03-03-2023_00h04m26s/needleRU_i35_0035_0014.caendat
RU : 4.90 MB/s
LF : 8.07 MB/s
Supposed Distance = 10 um
position of the target = 10.5 um
micrometer = 9.2 um
Voltage = 7.93 V
Plunger off set 60 um
Which means we are running 60 um + 10 um (read from position window of plunger) = 70 um. |
|
43
|
Fri Mar 3 02:23:45 2023 |
GJ | Problems | | Software | builder gate, TS offsets |
Data from current run - 35, with limited beam current and rates - see a recent post by Güray.
BU level, so what we see in Greware (both online & nearline).
Attached is the fold of Germaniums.
It seems way too large to me.
We are summing up the events and then, not surprisingly, having rubbish gamma-gamma matrices.
The gate is 1500 ns, while Ge are not so far away from each other.
Any fixed time differences should be corrected with LF configuration.
Having all Ge, ACS, and Neda TS-aligned at LF level, BU will do a good job with a reasonable short gate.
We need channel-by-channel TS differences.
The data we took and we are taking now can be recovered in terms of this correction later on.
Marcin can build the events correctly from LF level.
Let's try to do so with as short gates as possible and see again the gamma-gamma matrix and neutron-gated g-g
matrix. |
| Attachment 1: run_0035_BU_lenghts.png
|
|
|
42
|
Fri Mar 3 02:20:46 2023 |
mgb | Runs | | General | |
plunger run # 137
Beam dump 2.5 enA
Collimator 1.0 enA
02:21 /onlineNEDA_00/xData/hil099/run_0035_03-03-2023_00h04m26s/needleRU_i35_0035_0010.caendat
RU : 4.70 MB/s
LF : 7.92 MB/s
Supposed Distance = 10 um
position of the target = 10.7 um
micrometer = 9.8 um
Voltage = 7.89 V
Plunger off set 60 um
Which means we are running 60 um + 10 um (read from position window of plunger) = 70 um. |
|
41
|
Fri Mar 3 01:15:27 2023 |
mgb | Runs | | General | |
plunger run # 126
Earlier: CUP#6 100 enA
Now: CUP#6 50eNA
Beam dump 2.3 enA
Collimator 1.0 enA
RU : 5.44 MB/s
LF : 8.40 MB/s
Supposed Distance = 10 um
position of the target = 10.9 um
micrometer = 10.3 um
Voltage = 7.896 V
Plunger off set 60 um
Which means we are running 60 um + 10 um (read from position window of plunger) = 70 um. |
|
40
|
Fri Mar 3 00:09:19 2023 |
MP, AT | Runs | | | run 35 |
Started after beam current was reduced by a factor of 2
plunger run # 116
Earlier: CUP#6 100 enA
Now: CUP#6 50eNA
Beam dump 1.8 enA
Collimator 0.8 enA
The operator is asked to keep the beam dump current not larger than the present value.
Supposed Distance = 10 um
position of the target = 10 um
micrometer = 11.7 um
Voltage = 7.9 V
Plunger off set 60 um
Which means we are running 60 um + 10 um (read from position window of plunger) = 70 um.
Observed that detectors at theta 143 degrees count most. Is this because they see beam dump? |
|
39
|
Thu Mar 2 23:04:01 2023 |
GJ | Problem Fixed | | Hardware | Connection of the plunger cables, grounding, beam read-out for the operators |
Notes of the measurements with different conditions are attached.
Conclusion:
What is read out by the operators on the blue cable should be multiplied by 7 to get a real value in enA. |
| Attachment 1: Slp823030222550.pdf
|
|
|
38
|
Thu Mar 2 23:01:21 2023 |
A.T. | Runs | | General | Run 34 started |
Run 34 Started (33 was stopped due to acquisition problems)
Plunger Run : 105
Supposed Distance = 10 um
position of the target = 10 um
micrometer = 12.7 um
Voltage = 7.9 V
Plunger off set 60 um
Which means we are running 60 um + 10 um (read from position window of plunger) = 70 um.
at the first 10 min det # 5 was switched off
Ge det # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
old scalers: 5 2.5 8 5 8.5 3 5 1.5 5 8.5 8.5 7.5 2.7 2.7 5 kHz
new (Grzes) 1.7 1 3.2 1.8 3.6 0.9 1.7 0.45 1.7 3.5 3.2 3.1 1. 1. 1.7 kHz
beam dump current 3nA
det # 5 scaler 7.7 kHz
stoppped 00:02 because beam current was reduced byu a factor of 2 (see note on the next run) |
|
37
|
Thu Mar 2 17:28:21 2023 |
BS | Runs | | | Run 33 Started |
Run 33 Started
Plunger Run : 48
Supposed Distance = 10 um
position of the target = 10 um
micrometer = 6.5 um
Voltage = 7.957 V
Plunger off set 60 um
Which means we are running 60 um + 10 um (read from position window of plunger) = 70 um.
20:50 Observed beam dropped by a factor of 2 (1.5 enA on the beam dump). Asked the operator to improve beam.
run stop 22:53 acquisition problem |
|
36
|
Thu Mar 2 17:25:36 2023 |
BS | Runs | | General | Run 32 Stopped |
Run 32 Stopped |
|
35
|
Thu Mar 2 17:23:53 2023 |
BS | Runs | | General | Plunger Informations |
Plunger Run : 48
Supposed Distance = 10 um
position of the target = 10 um
micrometer = 6.5 um
Voltage = 7.957 V
Plunger off set 60 um
Which means we are running 60 um + 10 um (read from position window of plunger) = 70 um.
|
|
34
|
Thu Mar 2 16:40:45 2023 |
MP | Runs | | General | changing the plunger distance to minimum. |
Run 31 was stopped, because plunger distance is reduced to the mininimal one.
It takes time, in the meantime, after some break, run 32 was started, with no beam. |
|
33
|
Thu Mar 2 16:06:17 2023 |
A.T. | Runs | | General | |
Data
Position = 522.6
Supposed = 520
Plunger run = 32
Micrometer = 525.3
Run Data = /onlineNEDA_00/xData/hil099/run_0031_02-03-2023_11h18m31s/needleRU_i30_0031_0011.caendat
RU = 3.53 Mb/s
LF = 2.40 Mb/s
cables to colimeter are checked and replaced. |
|
32
|
Thu Mar 2 15:15:40 2023 |
mgb | Runs | | General | beam stopped. eagle is opened and run 30 continues |
Data
Position = 522.6
Supposed = 520
Plunger run = 32
Micrometer = 525.3
Run Data = /onlineNEDA_00/xData/hil099/run_0030_02-03-2023_11h18m31s/needleRU_i30_0030_0011.caendat
RU = 3.53 Mb/s
LF = 2.40 Mb/s
beam off and on and off. eagle is opened and run 30 continues
new cable is stucked
Cable test is going on |
|
31
|
Thu Mar 2 14:59:32 2023 |
mgb | Runs | | General | |
Data
Position = 522.6
Supposed = 520
Plunger run = 32
Micrometer = 525.3
Run Data = /onlineNEDA_00/xData/hil099/run_0030_02-03-2023_11h18m31s/needleRU_i30_0030_0011.caendat
RU = 3.53 Mb/s
LF = 2.40 Mb/s |
|
30
|
Thu Mar 2 13:50:50 2023 |
BS | Runs | | General | Run 30 Continueed |
EAGLE is closed now
We gave a break to test the cable connection of target, degrader, beam dump and collimator.
Run 30 continues to collect data, we did not stop it.
But not much usefull data in it. |
|
29
|
Thu Mar 2 12:09:44 2023 |
ost-mgb | Runs | | General | |
beam stop, |
|
28
|
Thu Mar 2 11:19:06 2023 |
BS | Runs | | General | Run 30 Starts |
We hane now g-g trigger started.
Run 30 started |
|
27
|
Thu Mar 2 11:17:54 2023 |
BS | Runs | | | Run 29 stopped |
We will change the trigger and we stopped the run number 29 |
|
26
|
Thu Mar 2 11:14:44 2023 |
ost-mgb | Runs | | General | |
un 29 with single gamma trigger
Plunger feedback system is not connected.
Data
Position = 522.6
Supposed = 520
Plunger run = 32
Micrometer = 525.3
Run Data = /onlineNEDA_00/xData/hil099/run_0029_02-03-2023_10h28m22s/needleRU_i29_0029_0021.caendat
RU = 40.1 Mb/s
LF = 12.5 Mb/s |
|
25
|
Thu Mar 2 10:18:14 2023 |
ost-mgb | Runs | | General | run 29 started |
Run 29 with single gamma trigger
Plunger feedback system is not connected.
Data
Position = 522.6
Supposed = 520
Plunger run = 32
Micrometer = 525.3
Run Data = /onlineNEDA_00/xData/hil099/run_0029_02-03-2023_10h28m22s/needleRU_i29_0029_0002.caendat
RU = 38.5 Mb/s
LF = 12.0 Mb/s
|